[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938991,606,1,"单选题","根据《标准施工招标文件》中合同条款的规定，下列可以同时补偿承包人工期、费用和利润的索赔事项是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取合同未约定的安全作业环境及安全施工措施的",false,{"key":16,"text":17,"correct":18},"B","因发包人原因造成工程质量达不到合同约定验收标准的",true,{"key":20,"text":21,"correct":14},"C","监理人未能按合同约定发出指示.指示延误或指示错误的",{"key":23,"text":24,"correct":14},"D","发包人提供的材料和工程设备，要求向承包人提前交货的","本题考查的是索赔管理。选项 AD，应予补偿费用；选项 C，应补补偿费用和（或）工期。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]