[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938990,606,1,"单选题","下列事件中，承包人即可得到费用补偿又可得到利润补偿的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","遇到不利物质条件",false,{"key":16,"text":17,"correct":14},"B","异常恶劣的气候条件导致工期延误",{"key":19,"text":20,"correct":21},"C","属发包人原因造成的工程缺陷或损坏",true,{"key":23,"text":24,"correct":14},"D","发包人提供的材料或工程设备不符合合同要求","本题考查的是索赔管理。在工期索赔中，选项 A，应予补偿费用和（或）工期；选项 B，应予补偿工期；选项 D，应予补偿费用和（或）工期。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]