[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938987":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938987,606,1,"单选题","根据《招标投标法》的规定，中标通知书发出之日起（ ）日，就是合同双方主体进行合同谈判的时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":14},"C","20",{"key":22,"text":23,"correct":24},"D","30",true,"本题考查的是施工合同订立。中标通知书发出之日起 30 日，就是合同双方主体进行合同谈判的时间。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]