[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938984,606,1,"单选题","下列关于变更权的表述，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","只有发包人可以提出变更，监理人负责通知",false,{"key":16,"text":17,"correct":14},"B","监理人签认的变更指示是可实施变更的最终依据",{"key":19,"text":20,"correct":21},"C","承包人收到变更指示后，应按变更指示进行变更工作",true,{"key":23,"text":24,"correct":14},"D","承包人可以根据经验对工程的非重要部分直接实施变更","本题考查的是工程费用管理。发包人和监理人均可以提出变更。变更指示只能由监理人发出，监理人发出变更指示前应征得发包人同意。承包人收到经发包人签认的变更指示后，方可实施变更。未经许可，承包人不得擅自对工程的任何部分进行变更。变更指示应说明变更的目的、范围、变更内容以及变更的工程量及其进度和技术要求，并附有关图纸和文件。承包人收到变更指示后，应按变更指示进行变更工作。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]