[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938982,606,1,"单选题","承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖的，监理人有权指示承包人钻孔探测或者揭开检查，无论工程隐蔽部分质量是否合格，由此增加的费用和（或）延误的工期由（ ）承担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人",false,{"key":16,"text":17,"correct":14},"B","发包人",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","监督机构","本题考查的是安全文明施工与环境保护。承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖的，监理人有权指示承包人钻孔探测或者揭开检查，无论工程隐蔽部分质量是否合格，由此增加的费用和（或）延误的工期均由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]