[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938976,606,1,"单选题","根据《标准施工招标文件》(2007 年版)，经验收合格工程的实际竣工日期，以( )为准， 并在工程接收证书中写明。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人收到竣工验收申请报告 56 天",false,{"key":16,"text":17,"correct":14},"B","发包人实际占有日期",{"key":19,"text":20,"correct":14},"C","验收合格日期",{"key":22,"text":23,"correct":24},"D","承包人提交竣工验收申请报告的日期",true,"经验收合格工程的实际竣工日期，以提交竣工验收申请报告的日期为准，并在工程 接收证书中写明。 发包人在收到承包人竣工验收申请报告 56 天后(内√)未进行验收的，视为验收合格，实际 竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的除外。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]