[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938974,606,1,"单选题","根据《标准施工招标文件》(2007 年版)，以下关于竣工验收与国家验收的说法，错误的 是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","国家验收是竣工验收的一部分",true,{"key":16,"text":17,"correct":18},"B","竣工验收所采用的各项验收和评定标准应符合国家验收标准",false,{"key":20,"text":21,"correct":18},"C","竣工验收指承包人完成了全部合同工作后，发包人按合同要求进行的验收",{"key":23,"text":24,"correct":18},"D","国家验收是政府有关部门，针对发包人全面组织实施的整个工程正式交付投运前的验收","需要进行国家验收的，竣工验收是国家验收的一部分。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]