[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938973,606,1,"单选题","根据《标准施工招标文件》(2007 年版)，承包人可向发包人提出费用和(或)工期索赔， 但不能提出利润索赔的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由于发包人的原因导致试运行失败的",false,{"key":16,"text":17,"correct":14},"B","发包人要求承包人提前竣工",{"key":19,"text":20,"correct":14},"C","由于发包人违约导致承包人暂停施工",{"key":22,"text":23,"correct":24},"D","发包人提供的材料不符合合同要求的",true,"A.由于发包人的原因导致试运行失败的——费用+合理利润 B.发包人要求承包人提前竣工——费用+奖金 C.由于发包人违约导致承包人暂停施工——费用和(或)工期+合理利润",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]