[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938967,606,1,"单选题","（ ）合同条件，项目的最终价格和要求的工期具有更大程度的确定性；由承包商承担项目实施的全部责任，雇主较少介入。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","红皮书",false,{"key":16,"text":17,"correct":14},"B","黄皮书",{"key":19,"text":20,"correct":21},"C","银皮书",true,{"key":23,"text":24,"correct":14},"D","绿皮书","本题考查的是新版FIDIC合同条件的适用范围和特点。《设计采购施工（EPC）\u002F交钥匙工程合同条件》，简称“银皮书”。该文件可适用于以交钥匙方式提供工厂或类似设施的加工或动力设备、基础设施项目或其他类型的开发项目，采用总价合同。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]