[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938959,606,1,"单选题","监理人在收到索赔通知书或有关索赔的进一步证明材料后的（ ）天内，将索赔处理结果答复承包人。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":14},"C","28",{"key":22,"text":23,"correct":24},"D","42",true,"本题考查的是索赔管理。监理人应按合同商定或确定追加的付款和（或）延长的工期，并在收到索赔通知书或有关索赔的进一步证明材料后的 42 天内，将索赔处理结果答复承包人。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]