[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938956,606,1,"单选题","根据《标准设计招标文件》，基准日之后设计文件遵守的法律发生重大变化时，设计人应向发包人提出遵守新规定的建议，发包人在收到建议后（ ）天内发出是否遵守新规定的指示。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","10","本题考查的是设计合同的主要内容。基准日之后设计文件遵守的法律发生重大变化时，设计人应向发包人提出遵守新规定的建议，发包人在收到建议后 7 天内发出是否遵守新规定的指示。发包人指示遵守新规定的，按照合同变更的约定执行。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]