[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938953,606,1,"单选题","设备采购合同中，买方在收到卖方提交的买卖双方签署的合同设备验收证书，经审核无误后 28 日内，向卖方支付合同价格的（ ）作为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20%；验收款",false,{"key":16,"text":17,"correct":18},"B","25%；验收款",true,{"key":20,"text":21,"correct":14},"C","20%；结清款",{"key":23,"text":24,"correct":14},"D","25%；结清款","本题考查的是设备采购合同的主要内容。设备采购合同中，买方在收到卖方提交的买卖双方签署的合同设备验收证书或已生效的验收款支付函正本一份并经审核无误后28日内，向卖方支付合同价格的25%。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]