[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938951,606,1,"单选题","设备采购合同生效后，买方在收到卖方开具的注明应付预付款金额的财务收据正本一份并经审核无误后 28 日内，向卖方支付签约合同价的（ ）作为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%；预付款",false,{"key":16,"text":17,"correct":18},"B","10%；预付款",true,{"key":20,"text":21,"correct":14},"C","20%；交货款",{"key":23,"text":24,"correct":14},"D","30%；交货款","本题考查的是设备采购合同的主要内容。设备采购合同生效后，买方在收到卖方开具的注明应付预付款金额的财务收据正本一份并经审核无误后 28 日内，向卖方支付签约合同价的 10%作为预付款。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]