[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938949,606,1,"单选题","下列关于发包人要求勘察人提前完成勘察的表述，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人不得压缩合理的勘察服务期限",false,{"key":16,"text":17,"correct":18},"B","提前完成勘察工作，可减少支付勘察费用",true,{"key":20,"text":21,"correct":14},"C","造成勘察费用增加的，所增费用由发包人承担",{"key":23,"text":24,"correct":14},"D","勘察人认为无法实施的，应在收到发包人书面指示后 7 天内提出异议","本题考查的是勘察合同的主要内容。除合同另有约定之外，发包人接受建议书的，不因提前完成勘察而减少勘察费用。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]