[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938944,606,1,"单选题","（ ）贯穿于工程项目实施的全过程，在项目建设的各阶段都必须用此来约束各方的责任、权利和义务。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同管理",true,{"key":16,"text":17,"correct":18},"B","安全管理",false,{"key":20,"text":21,"correct":18},"C","进度管理",{"key":23,"text":24,"correct":18},"D","费用管理","本题考查的是工程项目合同的特点和体系。合同管理贯穿工程项目实施的全过程，在项目建设的各阶段都必须用合同的形式来约束各方的责任、权利和义务。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]