[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938943,606,1,"单选题","FIDIC 是基于绿地设计—建造—运营方案来编写《设计- 建造和运营合同条件》的，项目建成后的运营期一般为（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",true,{"key":16,"text":17,"correct":18},"B","40",false,{"key":20,"text":21,"correct":18},"C","50",{"key":23,"text":24,"correct":18},"D","70","本题考查的是新版FIDIC合同条件的适用范围和特点。FIDIC是基于绿地设计—建造—运营方案来编写本合同条件的，项目建成后的运营期一般为20年",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]