[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938942,606,1,"单选题","FIDIC 施工合同条件下，如果逾期支付工程进度款，业主将承担延期付款的违约责任，延期付款的利息按（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","央行准备金率加 3%",false,{"key":16,"text":17,"correct":14},"B","银行贷款利率加 2%",{"key":19,"text":20,"correct":21},"C","银行贷款利率加 3%",true,{"key":23,"text":24,"correct":14},"D","银行存款利率加 2%","本题考查的是1999年版FIDIC施工合同条件的主要内容。FIDIC施工合同条件下，如果逾期支付工程进度款，业主将承担延期付款的违约责任，延期付款的利息按银行贷款利率加3%计算。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]