[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938941,606,1,"单选题","下列关于 FIDIC 合同条款中，关于竣工验收阶段合同管理的表述，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包商应提前 14 天将某一确定的竣工检验日期通知工程师",false,{"key":16,"text":17,"correct":14},"B","工程师应在收到承包商报送资料后的 14 天内进行竣工检验",{"key":19,"text":20,"correct":21},"C","工程师应在承包商所确定的竣工检验日期后 14 天内进行竣工检验",true,{"key":23,"text":24,"correct":14},"D","工程师应在承包商确定竣工检验日期事宜后 21 天内进行竣工检验","本题考查的是1999年版FIDIC施工合同条件的主要内容。承包商完成工程并准备好竣工报告所需报送的资料后，应提前21天将某一确定的日期通知工程师，说明此日后已准备好进行竣工检验。工程师应指示在该日期后14天内的某日进行。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]