[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938937":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938937,606,2,"多选题","有关业主对工程进度款的支付，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包商的报表经过工程师认可后业主应支付",false,{"key":16,"text":17,"correct":18},"B","业主应在接到进度款支付证书后及时给承包商付款",true,{"key":20,"text":21,"correct":14},"C","业主的付款时间不应超过工程师签发支付证书后的 56 天",{"key":23,"text":24,"correct":18},"D","如果逾期支付业主将承担延期付款的违约责任",{"key":26,"text":27,"correct":14},"E","延期付款的利息按银行存款利率加 3%计算","BD","本题考查的是 1999 版 FIDIC 施工合同条件的主要内容。承包商的报表经过工程师认可并签发工程进度款的支付证书后，业主应在接到证书后及时给承包商付款。业主的付款时间不应超过工程师收到承包商的月进度付款申请单后的 56 天。如果逾期支付，业主将承担延期付款的违约责任，延期付款的利息按银行贷款利率加 3%计算。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]