[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938936":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938936,606,2,"多选题","根据 FIDIC 施工合同条件，下列关于预付款的表述中，正确的包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预付款的具体金额在招标文件中确认",false,{"key":16,"text":17,"correct":14},"B","预付款应不少于合同总价的 20%",{"key":19,"text":20,"correct":21},"C","工程师在 21 天内签发预付款支付证书",true,{"key":23,"text":24,"correct":21},"D","预付款在支付工程进度款时按比例扣减",{"key":26,"text":27,"correct":21},"E","预付款保函金额始终保持与预付款等额","CDE","本题考查的是 1999 版 FIDIC 施工合同条件的主要内容。选项 AB 错误，预付款金额多少在专用条款内约定。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]