[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938933":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938933,606,2,"多选题","设计合同的阶段范围包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","方案设计",true,{"key":16,"text":17,"correct":14},"B","初步设计",{"key":19,"text":20,"correct":14},"C","施工图设计",{"key":22,"text":23,"correct":24},"D","编制设计概算",false,{"key":26,"text":27,"correct":24},"E","提供技术交底","ABC","本题考查的是设计合同的主要内容。阶段范围指工程建设程序中的方案设计、初步设计、扩大初步（招标）设计、施工图设计等阶段中的一个或多个阶段。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]