[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938923,606,2,"多选题","承包人向发包人可索赔费用和工期，不可索赔利润的情形有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","发现文物",true,{"key":16,"text":17,"correct":14},"B","监理指示错误",{"key":19,"text":20,"correct":21},"C","异常恶劣气候条件导致工期延误",false,{"key":23,"text":24,"correct":14},"D","遇到不利物质条件",{"key":26,"text":27,"correct":21},"E","不可抗力","ABD","本题考查的是施工合同履行。异常恶劣气候条件导致工期延误只可以索赔工期，不可抗力只能索赔部分费用和（或）工期。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]