[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938921":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938921,606,2,"多选题","合同履行过程中发生以下情形的，应按照合同约定进行变更（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加或减少合同中任何工作",true,{"key":16,"text":17,"correct":18},"B","专业分包",false,{"key":20,"text":21,"correct":14},"C","质量标准改变",{"key":23,"text":24,"correct":14},"D","改变工程的基线、标高、位置和尺寸",{"key":26,"text":27,"correct":18},"E","改变安全技术措施","ACD","本题考查的是施工合同履行。合同履行过程中发生以下情形的，应按照合同约定进行变更：（1）取消合同中任何一项工作，但被取消的工作不能转由发包人或其他人实施；（2）改变合同中任何一项工作的质量或其他特性；（3）改变合同工程的基线、标高、位置或尺寸；（4）改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序；（5）为完成工程需要追加的额外工作。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]