[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938917,606,1,"单选题","如由于买方原因在最后一批合同设备交货后 6 个月内未能开始考核，则买卖双方应在上述期限届满后（ ）签署验收款支付函。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7 日内",true,{"key":16,"text":17,"correct":18},"B","14 日内",false,{"key":20,"text":21,"correct":18},"C","21 日内",{"key":23,"text":24,"correct":18},"D","28 日内","本题考查的是设备采购合同的主要内容。如由于买方原因在最后一批合同设备交货后6 个月内未能开始考核，则买卖双方应在上述期限届满后 7 日内签署验收款支付函。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]