[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938913,606,1,"单选题","经验收合格工程的实际竣工日期，以（ ）为准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","验收合格日期",false,{"key":16,"text":17,"correct":18},"B","提交竣工验收申请报告的日期",true,{"key":20,"text":21,"correct":14},"C","组织竣工验收日期",{"key":23,"text":24,"correct":14},"D","发包人使用日期","本题考查的是施工合同履行。经验收合格工程的实际竣工日期，以提交竣工验收申请报告的日期为准，并在工程接收证书中写明。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]