[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938911,606,1,"单选题","合同变更指示通过（ ）发出。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","承包人",{"key":19,"text":20,"correct":21},"C","监理人",true,{"key":23,"text":24,"correct":14},"D","设计人","本题考查的是施工合同履行。变更指示只能由监理人发出，监理人发出变更指示前应征得发包人同意。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]