[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938907,606,1,"单选题","下列关于FIDIC施工合同条件下缺陷通知期的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缺陷通知期即国内施工文本所指的工程保修期",true,{"key":16,"text":17,"correct":18},"B","缺陷通知期自工程接收证书中写明的竣工日开始",false,{"key":20,"text":21,"correct":18},"C","缺陷通知期为考验工程动态进行中是否达到合同要求而设置",{"key":23,"text":24,"correct":18},"D","缺陷通知期内工程出现质量问题由承包商负责","缺陷通知期即国内施工文本所指的缺陷责任期，自工程接收证书中写明的竣工日开 始，至工程师颁发履约证书为止的日历天数。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]