[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938905":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938905,606,2,"多选题","根据FIDIC施工合同条件，下列关于工程进度款的表述中，正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程量清单中的工程量不能作为工程结算的依据",true,{"key":16,"text":17,"correct":18},"B","采用单价合同的项目应以图纸工程量作为支付依据",false,{"key":20,"text":21,"correct":14},"C","工程款逾期支付，业主应按银行贷款利率加3%支付利息",{"key":23,"text":24,"correct":14},"D","工程师应在收到承包商支付报表后28天内按核实结果签发支付证书",{"key":26,"text":27,"correct":14},"E","业主的付款时间不应超过工程师收到承包商的月进度付款申请单后的56天","ACDE","采用单价合同的施工工作内容应以计量的数量作为支付进度款的依据，而总价合同 可以按图纸工程量作为支付依据，仅对变更部分予以计量。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]