[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938898,606,1,"单选题","根据《标准勘察招标文件》，关于周期延误的表述错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","出现合同规定的异常恶劣气候条件导致周期延误的，勘察人有权要求发包人延长周期",false,{"key":16,"text":17,"correct":14},"B","勘察人发现地下文物时，有权要求发包人延长周期",{"key":19,"text":20,"correct":14},"C","勘察人原因造成周期延误，勘察人应支付逾期违约金",{"key":22,"text":23,"correct":24},"D","由于行政管理部门审查延迟造成周期延误的，由勘察人承担",true,"由于出现合同规定的异常恶劣气候条件、不利物质条件等因素导致周期延误的，勘 察人有权要求发包人延长周期和(或)增加费用。 勘察人发现地下文物或化石时，应按规定及时报告发包人和文物部门，并采取有效措施进行 保护；勘察人有权要求发包人延长周期和(或)增加费用。 由于勘察人原因造成周期延误，勘察人应支付逾期违约金。 由于行政管理部门审查延迟造成费用增加和(或)周期延误的，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]