[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938897,606,1,"单选题","根据《标准勘察招标文件》，因发包人原因造成合同签订之日起( )天内未能发出开始 勘察通知的，勘察人有权提出价格调整要求，或者解除合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","90",true,{"key":16,"text":17,"correct":18},"B","7",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","28","(1)符合合同约定的开始勘察条件的，发包人应提前 7 天向勘察人发出开始勘察通 知。勘察服务期限自开始勘察通知中载明的开始勘察日期起计算。(2)因发包人原因造成合同签订之日起 90 天内未能发出开始勘察通知的，勘察人有权提出价 格调整要求，或者解除合同。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]