[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938892":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":21,"analysis":24},938892,606,1,"单选题","根据《标准设备采购招标文件》，由于买方原因合同设备在三次考核中均未能达到技术性 能考核指标，买卖双方应在考核结束后 7 日内签署( )。",[11,15,17,20],{"key":12,"text":13,"correct":14},"A","合同设备验收证书",false,{"key":16,"text":13,"correct":14},"B",{"key":18,"text":19,"correct":14},"C","质量保证期届满证书",{"key":21,"text":22,"correct":23},"D","验收款支付函",true,"由于买方原因合同设备在三次考核中均未能达到技术性能考核指标，买卖双方应在 考核结束后 7 日内签署验收款支付函。卖方有义务在验收款支付函签署后 12 个月内应买方要求 提供相关技术服务，协助买方采取一切必要措施使合同设备达到技术性能考核指标。在上述 12 个月的期限内，如合同设备经过考核达到或视为达到技术性能考核指标，则买卖双方应按照合同 约定签署合同设备验收证书。",{"id":6,"name":26,"category":27,"favorite":28},"工程项目组织与管理","建筑工程",0]