[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938891,606,1,"单选题","由于卖方原因未能达到技术性能考核指标时，为卖方进行考核的机会不超过( )次。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","二",false,{"key":16,"text":17,"correct":18},"B","三",true,{"key":20,"text":21,"correct":14},"C","五",{"key":23,"text":24,"correct":14},"D","一","由于卖方原因未能达到技术性能考核指标时，为卖方进行考核的机会不超过三次。由于买方原因未能达到技术性能考核指标时，为买方进行考核的机会不超过三次。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]