[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938889,606,2,"多选题","根据《工程建设项目施工招标投标办法》的规定，施工招标项目工期较长的，招标文件 中可以规定( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","价格调整因素",true,{"key":16,"text":17,"correct":14},"B","工程造价指数体系",{"key":19,"text":20,"correct":14},"C","价格调整方法",{"key":22,"text":23,"correct":24},"D","需调整的合同价款",false,{"key":26,"text":27,"correct":24},"E","需调整的工程费用","ABC","根据《工程建设项目施工招标投标办法》的规定，施工招标项目工期较长的，招标 文件中可以规定工程造价指数体系、价格调整因素和调整方法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]