[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938885,606,1,"单选题","根据《标准施工招标文件》(2007年版)，合同进度计划是指经( )批准的施工进度计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监督人",false,{"key":16,"text":17,"correct":14},"B","承包人",{"key":19,"text":20,"correct":21},"C","监理人",true,{"key":23,"text":24,"correct":14},"D","投资人","经监理人批准的施工进度计划称合同进度计划，是控制合同工程进度的依据。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]