[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938882,606,1,"单选题","根据《标准施工招标文件》(2007 年版)，承包人按合同约定完成了包括缺陷责任期内的全 部承包工作后，发包人应付给承包人的金额称为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同价格",true,{"key":16,"text":17,"correct":18},"B","签约合同价",false,{"key":20,"text":21,"correct":18},"C","合同结算价格",{"key":23,"text":24,"correct":18},"D","合同决算价格","签约合同价——指签定合同时合同协议书中写明的，包括了暂列金额、暂估价的合 同总金额。合同价格——指承包人按合同约定完成了包括缺陷责任期内的全部承包工作后，发包 人应付给承包人的金额，包括在履行合同过程中按合同约定进行的变更和调整。因此，发包人和 承包人最终结算的合同价款是合同价格，而不是最初招标确定的合同签约价。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]