[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938876":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938876,606,2,"多选题","根据FIDIC 施工合同条件，下列关于预付款的表述中，正确的包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预付款的具体金额在招标文件中确认",false,{"key":16,"text":17,"correct":14},"B","预付款应不少于合同总价的60%",{"key":19,"text":20,"correct":21},"C","工程师在21天内签发预付款支付证书",true,{"key":23,"text":24,"correct":21},"D","预付款在支付工程进度款时按比例扣减",{"key":26,"text":27,"correct":21},"E","预付款保函金额始终保持与预付款等额","CDE","本题考查的是 1999 年版 FIDIC 施工合同条件的主要内容。选项 A 错误，预付款的数额由承包商在投标书内确认；选项 B 错误，通用条件的条款规定，为了帮助承包商解决订购大宗主要材料和设备所占用资金的周转，订购物资经工程师确认合格后，按发票价值 80%作为设备和材料预付的款额，包括在当月应支付的工程进度款内。双方也可以在专用合同条件内修正这个百分比，目前施工合同的约定通常在 60%～90%范围内。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]