[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938874":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938874,606,2,"多选题","下列关于FIDIC 施工合同条件下缺陷通知期的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","缺陷通知期不同于国内施工合同所指的工程保修期",false,{"key":16,"text":17,"correct":18},"B","缺陷通知期自工程接收证书中写明的竣工日开始",true,{"key":20,"text":21,"correct":14},"C","承包商应在缺陷通知期开始前将工程所有工作完成",{"key":23,"text":24,"correct":18},"D","缺陷通知期内工程出现质量问题由承包商负责",{"key":26,"text":27,"correct":18},"E","缺陷通知期为考验工程动态进行中是否达到合同要求而设置","BDE","本题考查的是 1999 年版 FIDIC 施工合同条件的主要内容。选项 A 错误，缺陷通知期即国内施工文本所指的缺陷责任期；选项 C 错误，扫尾、清理施工现场及不影响工程使用的某些次要部位缺陷修复等剩余工作允许承包商在缺陷通知期内继续完成。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]