[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938872,606,1,"单选题","根据FIDIC 施工合同条件，下列关于工程进度款的表述中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量清单中的工程量可以作为工程结算的依据",false,{"key":16,"text":17,"correct":14},"B","采用单价合同的项目应以图纸工程量作为支付依据",{"key":19,"text":20,"correct":14},"C","工程款逾期支付，业主应按银行贷款利率加2%支付利息",{"key":22,"text":23,"correct":24},"D","工程师应在收到承包商支付报表后28天内按核实结果签发支付证书",true,"本题考查的是 1999 年版 FIDIC 施工合同条件的主要内容。选项 A 错误，工程量清单中的工程量不可以作为工程结算的依据；选项 B 错误，采用单价合同的施工工作内容应以计量的数量作为支付进度款的依据；选项 C 错误，如果逾期支付将承担延期付款的违约责任，延期付款的利息按银行贷款利率加 3%计算。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]