[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938868":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938868,606,2,"多选题","FIDIC 合同条件下，承包商编制施工进度计划时应说明拟采用的（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","进度计划安排",true,{"key":16,"text":17,"correct":14},"B","施工组织方案",{"key":19,"text":20,"correct":21},"C","月支付费用",false,{"key":23,"text":24,"correct":14},"D","施工方法",{"key":26,"text":27,"correct":21},"E","预付款扣还方式","ABD","本题考查的是 1999 年版 FIDIC 施工合同条件的主要内容。承包商收到开工通知后的 28天内，按工程师要求的格式和详细程度提交施工进度计划，说明为完成施工任务而打算采用的施工方法、施工组织方案、进度计划安排，以及按季度列出根据合同预计应支付给承包人费用的资金估算表。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]