[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938862":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938862,606,2,"多选题","在履行合同过程中，由于( )原因造成勘察服务期限延误的，发包人应当延长勘察 服务期限并增加勘察费用。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","发包人原因造成合同变更",true,{"key":16,"text":17,"correct":14},"B","出现合同规定的异常恶劣气候条件导致周期延误",{"key":19,"text":20,"correct":14},"C","勘察人发现地下文物，及时报告发包人和文物部门，并采取有效保护措施",{"key":22,"text":23,"correct":14},"D","行政管理部门审查延迟造成费用增加和周期延误",{"key":25,"text":26,"correct":27},"E","勘察人原因造成周期延误",false,"ABCD","由于勘察人原因造成周期延误，勘察人应支付逾期违约金。在履行合同过程中，由 于发包人的下列原因造成勘察服务期限延误的，发包人应当延长勘察服务期限并增加勘察费用， 具体方法在合同中约定： (1)合同变更； (2)未按合同约定期限及时答复勘察事项； (3)因发包人原因导致的暂停勘察； (4)未按合同约定及时支付勘察费用； (5)发包人提供的基准资料错误； (6)未及时履行合同约定的相关义务； (7)未能按照合同约定期限对勘察文件进行审查； (8)发包人造成周期延误的其他原因。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]