[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938857":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938857,606,2,"多选题","根据《标准施工招标文件》（2007 年版），下列关于解决合同争议的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","在争议评审、仲裁或诉讼过程中，发包人和承包人均可共同努力友好协商解决争议",true,{"key":16,"text":17,"correct":14},"B","发包人和承包人应在开工日后的28天内或在争议发生后，协商成立争议评审组",{"key":19,"text":20,"correct":14},"C","争议评审组的评审意见并不具有法律强制性",{"key":22,"text":23,"correct":24},"D","友好协商解决不成的，才可以向约定的仲裁委员会申请仲裁",false,{"key":26,"text":27,"correct":24},"E","合同中可同时将仲裁和诉讼约定为解决争议的方式","ABC","本题考查的是施工合同履行。选项 D 错误，发包人和承包人在履行合同中发生争议的，可以友好协商解决或者提请争议评审组评审；故友好协商并非仲裁的前置条件；选项 E 错误，仲裁或者诉讼，只能选择其一。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]