[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938856":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938856,606,2,"多选题","根据《标准施工招标文件》（2007 年版），下列关于隐蔽工程检查的说法，错误的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","承包人自检确定隐蔽工程具备覆盖条件的，应通知监理人在约定的期限内检查",false,{"key":16,"text":17,"correct":14},"B","监理人检查隐蔽工程发现质量不合格的，承包人应自费完成修复",{"key":19,"text":20,"correct":14},"C","监理人未按时进行检查也未提出延期要求的，视为隐蔽工程检查合格",{"key":22,"text":23,"correct":24},"D","监理人检查完毕且承包人覆盖隐蔽工程后，监理人不能再要求对隐蔽工程进行重新检查",true,{"key":26,"text":27,"correct":24},"E","承包人私自将隐蔽工程覆盖的，监理人有权指示承包人揭开检查，如果质量合格，由此增加的费用由发包人承担","DE","本题考查的是施工合同履行。选项 D 错误，承包人覆盖工程隐蔽部位后，监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行，并在检验后重新覆盖恢复原状；选项 E 错误，经检验证明工程质量符合合同要求的，由发包人承担由此增加的费用和（或）工期延误，并支付承包人合理利润；经检验证明工程质量不符合合同要求的，由此增加的费用和（或）工期延误由承包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]