[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938854,606,2,"多选题","根据《标准施工招标文件》（2007 年版），下列情形中，应由发包人承担由此增加的费用并支付承包人合理利润的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在施工现场遇到不可预见的地质条件",false,{"key":16,"text":17,"correct":18},"B","提供图纸延误",true,{"key":20,"text":21,"correct":18},"C","未按合同约定及时支付预付款、进度款",{"key":23,"text":24,"correct":18},"D","增加合同工作内容",{"key":26,"text":27,"correct":14},"E","异常恶劣的气候条件造成工程暂停","BCD","本题考查的是施工合同履行。选项 A，发包人承担延误的工期和（或）增加的费用；选项 E，发包人承担延误的工期。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]