[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938851,606,1,"单选题","根据《标准施工招标文件》（2007 年版），承包人仅可向发包人提出费用和（或）工期索赔的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由于发包人的原因导致试运行失败的",false,{"key":16,"text":17,"correct":14},"B","发包人要求承包人提前竣工",{"key":19,"text":20,"correct":14},"C","由于发包人违约导致承包人暂停施工",{"key":22,"text":23,"correct":24},"D","发包人提供的材料不符合合同要求的",true,"本题考查的是施工合同履行。选项 A 的情形可索赔费用＋合理利润；选项 B 的情形，可索赔费用＋奖金；选项 C 的情形，可索赔费用和（或）工期＋合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]