[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938844,606,1,"单选题","根据《标准施工招标文件》（2007 年版），下列关于合同变更的说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人和监理人均可提出变更",false,{"key":16,"text":17,"correct":18},"B","发包人可直接向承包人发出变更指示",true,{"key":20,"text":21,"correct":14},"C","承包人收到经发包人签认的变更指示后，方可实施变更",{"key":23,"text":24,"correct":14},"D","若承包人认为变更指示不能执行，应立即说明理由","本题考查的是施工合同履行。变更指示只能由监理人发出，监理人发出变更指示前应征得发包人同意。承包人收到经发包人签认的变更指示后，方可实施变更。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]