[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938842,606,1,"单选题","根据《建设工程施工合同（示范文本）》，下列合同文件内容不一致时，优先解释等级最高的文件是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同协议书",true,{"key":16,"text":17,"correct":18},"B","中标通知书",false,{"key":20,"text":21,"correct":18},"C","投标函及其附录",{"key":23,"text":24,"correct":18},"D","合同条款","本题考查的是施工合同订立。构成工程施工合同的文件及解释顺序：（1）合同协议书；（2）中标通知书；（3）投标函及投标函附录；（4）专用合同条款；（5）通用合同条款；（6）技术标准和要求；（7）图纸；（8）已标价工程量清单；（9）其他合同文件。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]