[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938830":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938830,606,2,"多选题","根据《中华人民共和国招投标法实施条例》，下列关于两阶段招标的说法，错误的是有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","两阶段招标适用于所有类型的招标项目",true,{"key":16,"text":17,"correct":14},"B","在第一阶段招标人应向投标人发出招标文件",{"key":19,"text":20,"correct":21},"C","在第一阶段招标人应要求投标人提交技术建议",false,{"key":23,"text":24,"correct":14},"D","在第二阶段招标人应与投标人就技术建议内容进行协商和讨论",{"key":26,"text":27,"correct":21},"E","招标文件要求提交投标保证金的，投标人应在第二价段按规定缴纳","ABD","本题考查的是工程项目招标范围和规模标准。选项A错误，两阶段招标适用于技术复杂或者无法精确拟定技术规格的项目；选项B错误，在第二阶段招标人应向投标人发出招标文件；选项D错误，在第一阶段招标人应与投标人就技术建议内容进行协商和讨论。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]