[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938817":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938817,606,2,"多选题","投标团队在项目咨询招标初期应做的工作有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","认真填报、及时递交资格预审申请文件",true,{"key":16,"text":17,"correct":14},"B","编制提交本咨询单位“实力介绍文件”",{"key":19,"text":20,"correct":14},"C","制定初步投标计划",{"key":22,"text":23,"correct":24},"D","组织合同谈判",false,{"key":26,"text":27,"correct":24},"E","编制投标文件","ABC","本题考查的是国际工程咨询服务投标。投标团队在项目咨询招标初期应做好以下工作：（1）认真填报、及时递交资格预审申请文件，积极争取列入短名单中；（2）编制并主动向招标人提交本咨询单位“实力介绍文件”；（3）加强与客户的联系，详细了解客户对咨询服务的要求；（4）通过各种渠道，尽可能收集与项目有关的信息资料。了解项目所在国家或地区的政治、经济、文化、法律、自然条件等方面的情况；（5）研究制定初步的投标计划，认真考虑承担咨询任务的专家人选。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]