[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938797":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938797,606,1,"单选题","下列项目必须进行招标的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","某总投资 2000 万元的别墅建设项目",false,{"key":16,"text":17,"correct":18},"B","某设计费为 120 万元的保障性住房项目",true,{"key":20,"text":21,"correct":14},"C","某施工单项合同价 250 万元的供热市政工程项目",{"key":23,"text":24,"correct":14},"D","某施工图预算 300 万元的施工企业自建自用宿舍项目","本题考查的是工程项目招标范围和规模标准。三项规定范围内的项目，其勘察、设计、施工、监理以及与工程建设有关的重要设备、材料等的采购达到下列标准之一的，必须进行招标：（1）施工单项合同估算价在400万元人民币以上的；（2）重要设备、材料等货物的采购，单项合同估算价在200万元人民币以上的；（3）勘察、设计、监理等服务的采购，单项合同估算价在100万元人民币以上。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]