[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938770,606,1,"单选题","下列关于标底和最高投标限价编制要求的表述，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标项目可以不设标底",false,{"key":16,"text":17,"correct":14},"B","一个招标工程只能编制一个标底",{"key":19,"text":20,"correct":14},"C","招标人可根据项目特点决定是否编制标底",{"key":22,"text":23,"correct":24},"D","招标人应明确最低投标限价或最高投标限价",true,"本题考查的是编制工程标底或最高投标限价。招标人设有最高投标限价的，应当在招标文件中明确最高投标限价或者最高投标限价的计算方法。招标人不得规定最低投标限价。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]